ESR to build urban distribution center in Delhi

ESR Group is making significant progress in constructing its Urban Distribution Centre in Delhi. The project consists of two buildings, and construction is underway for both. Building 1 is approximately 30% complete, with the first-floor slab currently being laid out. Scaffolding work is in progress for building 2, which is currently 20% complete. ESR aims to complete the construction of this multilevel distribution centre by the end of 2023.
Situated in Alipur, northwest Delhi, the site will enable just-in-time delivery to 2 million customers in Rohini, Shalimar Bagh, Pitampura, Ashok Vihar, and Model Town, all reachable within 20 minutes. The location offers excellent connectivity throughout the city via the Outer Ring Road, just a 5-minute drive from the site, and the Eastern Peripheral Expressway (KMP). It also provides access to the neighbouring states of Haryana and Punjab via NH44. The upcoming UER 2 starts from NH 44 at Alipur, close to ESR’s Urban Distribution Centre, will connect Rohini, Mundka, Najafgarh, and Dwarka and end at Delhi–Gurgaon Expressway on National Highway 48 and make IGI airport accessible from this location within 40 minutes.